So we’re only six working days into our SkyRanger Nynja build and it’s already beginning to take shape. The build has been very straightforward so far and as you can see in the photos, the design is simple and robust. We managed to get the airframe onto its main wheels by day 5 and on day 6 (Sunday), we got the nose gear fitted. Check back on a regular basis to see the progress of our build!

The main cabin area after the first few hours work

The main cabin area after the first few hours work

On day 2 we fitted the cabin floor and some more bracing around the cabin area

On day 2 we fitted the cabin floor and some more bracing around the cabin area

The rudder pedals were installed on day 3

The rudder pedals were installed on day 3

The aft fuselage went together on day 4

The aft fuselage went together on day 4

The main landing gear was the focus of day 5

The main landing gear was the focus of day 5

By the end of day 5 the airframe now sits on the undercarriage

By the end of day 5 the airframe now sits on the undercarriage

End of day 5

End of day 5

image015

On day 6 the nose gear was installed as well as the brake calipers